|
Test results
for a group of parts may be requested by
vehiclemakers to verify these results, especially
if the particular part has failed when installed
on vehicles.
Traditional gathering and reporting of
this information has been manual; manual
review of data that was manually recorded
on production sheets, and then manual consolidation
of test results, serial numbers, etc. and
entry onto a spreadsheet. The process culminates
in a report taking four to six weeks to
complete to send to the customer.
Situation
The testing
policy of a Tier 1 supplier of steering
wheel assemblies was to e-test, or electronically
test, every horn as it was installed in
the steering wheel assembly at the supplier¡s
factory. The criteria gathered by this test
were test values and connections that control
the horn and the cruise control. About 25,000
steering wheels are produced per week at
the plant
Challenge
The Tier 1
supplier needed to provide a customer with
a report compiling all e-test results for
horns and cruise controls installed during
the steering wheel assembly for a consecutive
three-month period. Test results of more
than 300,000 steering wheels were required.
Manually preparing this report would
consume 15 days of a full-time person, either
internally (taken from a current position)
or someone hired externally. If the Tier
1 wanted to extract the test values from
the PLC, a programmer, with PLC language
expertise, would be required to write a
program to extract the data and format it
into a readable report. If the PLC did not
have a large storage capacity of information,
some of the data may have been written over.
Without an internal resource to do this,
the cost would have been about $6,000 and
would have taken about five days.
Solution
The supplier
was using VIA's manufacturing information
tool, MAN-IT, which collected,
sorted and filed this data continually,
without write-over. MAN-IT
was configured to capture process variables
and test results (pass, fail, and the details)
at each operation. The data the customer
requested had been captured and stored in
an electronic format.
Result
produced a
report with the requested information within
15 minutes of the vehiclemaker¡s request,
allowing it to replace only 12 steering
wheels because of the detailed results from
the MAN-IT report. It had not
expected the report for at least several
weeks, and was prepared to replace thousands
more based on past experience. This quick
response exceeded the customer's expectations
and allowed the vehiclemaker to quickly
assess the situation with the steering wheels
in a positive and cost-efficient manner
that gained status for the supplier and
saved the OEM money.
|